SBL 1

 0    16 Datenblatt    michallekawa
mp3 downloaden Drucken spielen überprüfen
 
Frage English Antworten English
Project completion report content.
PCR
Lernen beginnen
The extent of project objectives achieving.
Post-project review (PPR) characteristics.
2
Lernen beginnen
This examines the project looking for areas that did not go smoothly and for those that did. | the performance of the project team members.
Types of review that should be carried out after the project is completed:
2
Lernen beginnen
A post-project review. | A post-implementation review.
PPR | PIR
This is about the project. | This is about what the project achieved.
Project triple constraint.
Lernen beginnen
Scope. | Time. | Cost.
IR – Information connectivity
Lernen beginnen
Show a holistic picture of the combination of interrelated factors, | that enable the company to create value over time.
Observable benefits examples:
3 | Project four benefits
Lernen beginnen
Improved staff motivation. | Ability to attract more able staff. | Further brand awareness.
Observable benefits characteristics:
3
Lernen beginnen
There are often intangible | and difficult to objectively measure. | Value often determined by the view of qualified observers.
Measurable benefits examples:
3
Lernen beginnen
Number of rivals leaving the market. | The increase in market share. | Increases in local house prices.
Measurable benefits characteristics:
3
Lernen beginnen
Objective measure | but difficult to assess. | and usually the value of the change can only by determined retrospectively.
Quantifiable benefits examples:
3
Lernen beginnen
Reduction in environmental emissions. | Reduction in wastage. | Reduction in product returns.
Quantifiable benefits characteristics:
2
Lernen beginnen
Can by reliably forecast in advance. | But financial value may be difficult to forecast (is external or variable).
Unlike measurable benefits.
Financial benefits examples
2
Lernen beginnen
Extra sales. | Saving from economies of scale.
Can be given an objective financial value - either in terms of a revenue increase or a cost reduction.
Boundaryless organisations types:
3
Lernen beginnen
Hollow structure. | Modular structure. | Virtual structure.
Virtual structure:
2
Lernen beginnen
Organisation is made up of a collaboration of other organisational parts. | To respond to exceptional, often temporary market opportunities.
Modular structure:
Lernen beginnen
Outsource parts from different providers and assemble into a product.
Minimizing the specialization and specialists needed. Minimizing overhead.
Hollow structure:
Lernen beginnen
All non-core operations are outsourced leaving the company to concentrate on its core competence eg design of new products.
Like accounting, human resources, legal services and manufacturing could be outsourced.

Sie müssen eingeloggt sein, um einen Kommentar zu schreiben.